Beacon To The Future

Project Timeline History

Check out highlights from the project timeline below. Also see additional updates on our Facebook page and read some blog posts from the project.

  • November 14-16
    Dedication Weekend!
  • November 13

    Ready for dedication! View the beautiful results!

  • Sept - Nov

    Contractors wrap up remaining tasks (installing central stair carpet, touch-up painting, etc.)

  • August 29

    Brothers move in at 5:00PM.

    Rush starts 8:00AM next day!

    We made it!

  • August 14
    Almost ready for move-in! -- Watch the mad rush to rush on video!
  • Jan - August

    Construction!

    Brothers live in apartments for spring term and summer.

  • January 16
    Rear stairs and basement floor removed - watch the video update!
  • January 2
    Demo continues -- watch the video tour!
  • December 30
    Major demolition work on zero floor! Goodbye old kitchen!
  • December 23

    Construction begins!!

    Workers disconnect utilities, prepare for demolition work.

  • December 20
    Move Out is Complete! On schedule!
  • December 16-20
    Brothers take final exams and then move out their final personal items!
  • Fall Term 2013
    As brothers live in the house for the final pre-renovation term, a carefully orchestrated purge and move-out occurs in phases, starting with Work Week, August/September 2013.